Walnut Woods sidewalk project planned

By on October 25, 2010

SUGAR GROVE—The Sugar Grove Village Board on Tuesday voted 5-0 to hire D’ Land Construction LLC to replace deteriorating sidewalks in the Walnut Woods subdivision.

The village’s construction agreement with D’Land also calls for replacing damaged driveway aprons and handicap ramps in the subdivision. In total, the village will replace 9,065 square feet of concrete and 815 square feet of asphalt in the subdivision.

The project will be finished by Nov. 30, weather permitting.